JELLY BEANS GROUP Co.,Ltd. [3070.T]
TOKYO, Apr 28 (Pulse News Wire) – Jelly Beans Group CO.,LTD. (3070.T) announced adjustments to the schedule for establishing its special purpose company (SPC).
Originally set for April 2026, the completion and operational launch of the Takusa Refinery had to be postponed due to additional construction work needed during the fuel tank production phase. As a result, the company revised the project timeline, pushing back the anticipated operation commencement from April to July 2026.
In detail, the initial plan outlined in the April 2 announcement included setting up the SPC within April 2026 and commencing operations in the same month. However, the recent developments necessitated a reassessment, leading to the updated schedule being released.
Despite the extension, the company assured stakeholders that there would be no impact on the overall project objectives or timelines beyond July 2026.