Enex Infrastructure Investment Corporation [9286.T]
TOKYO, Apr 21 (Pulse News Wire) – Enex Infrastructure Investment Corporation (9286.T) completed the partial restart of its Kozuchi Solar Power Plant B following a fire incident reported on April 17. The plant, located in Koshu City, Gunma Prefecture, experienced a halt in operations since April 13 due to safety concerns.
An emergency inspection conducted by O&M operators found no significant issues except for two power converters which remain offline pending further checks scheduled for early May. Investor concerns have been acknowledged, and the company stated it will update stakeholders on any progress in the recovery process. As of now, one converter remains out of service due to damage, while another awaits manufacturer inspections. Both affected units consist of two inverters each; however, only one inverter per unit is currently non-operational, allowing for half-capacity operation.
In total, ten power converters are installed at Kozuchi B, comprising nineteen inverters, seventeen of which are now operational. At Kozuchi A, all two power converters, totaling four inverters, have resumed normal operations. Kazuhisa Matsuzuka, Executive Officer of Enex Infrastructure Investment Corporation, extended apologies for any inconvenience caused to investors during this period. Further updates will be communicated as necessary.
🟢 Confidence: High AI-translated content.